3. Arnhem Highway
| Project | Arnhem Highway CH57.20KM Truck Parking Bay – T and Arnhem Highway CH54.10km Upgrade Truck Parking Bay simultaneously carried out collectively. |
| Awarded by | Department of Infrastructure NT Government |
| Commencement | |
| Completion | 12-08-2013 |
| Value | $ 1,184,000.00 |
| Works consisted of |
|---|
| Traffic management |
| Environmental management |
| Location & protection of services |
| Surveying works |
| Clearing & Grubbing approximately 13,000m2 |
| Earthworks |
| Preparation & maintenance of surfaces |
| Relocation of overhead transmission line |
| Relocation of light pole |
| Road formation |
| Drainage formation |
| Construct & concrete weighing pad |
| Install culverts and construct headwalls |
| Protection works including stone pitching, reno mattress and geotextile fabric |